Wonder if you can help, I haven't used project for a while (am using version
2000). I have split my project into Stages. The duration dates are
accumulating first 3 stages , then the subsequent Stages have just
accumulated the days in the sub tasks of each section.

How can I make it uniform?
 
J

John

Edwards said:
Wonder if you can help, I haven't used project for a while (am using version
2000). I have split my project into Stages. The duration dates are
accumulating first 3 stages , then the subsequent Stages have just
accumulated the days in the sub tasks of each section.

How can I make it uniform?

Edwards,
I guess we need some clarification. First, what exactly do you mean by,
"...split my project into stages."? In other words, what is your file
structure? Are these "stages" summary lines or some other hierarchy?
Second, duration is time span, not dates. So what do you mean by, "...
duration dates are accumulating first 3 stages."?

If you can give us a little better explanation of how your file is
structured and what you want to see, then maybe we can help you.

John