When i enter 2 days duration of a task starting on 14 November, it
shows end date as 16 November.
Ideally it should be 15 November. But if i enter 7 days for a task
starting on 14 November, it
shows as 23 November, taking into consideration that Saturday n Saunday
is off.
I am unable to understand this. kindly help me with this....!!!