P
pablo_BR
Hello Doctors!!!
Have you ever seen this bug?
I´ve built a plan in a machine with Project Standart 2003 and when
opening this plan in a machine with Project Standard 2007, some task
durations are lost!
The problem only happens in tasks which I selected type "fixed
duration", have entered some duration in days, have a resource
assigned, but work is "0 hours". (this setting is because I don´t want
to track work on these tasks).
So, example, if I have a task which has work=0hrs; duration=3days in
Project2003, when I open it in Project 2007 it will show work=0hrs;
duration=0days.
I tried to equalize the "Options" parameters in both machines, but the
problem is still there. Why?
Have you ever seen this bug?
I´ve built a plan in a machine with Project Standart 2003 and when
opening this plan in a machine with Project Standard 2007, some task
durations are lost!
The problem only happens in tasks which I selected type "fixed
duration", have entered some duration in days, have a resource
assigned, but work is "0 hours". (this setting is because I don´t want
to track work on these tasks).
So, example, if I have a task which has work=0hrs; duration=3days in
Project2003, when I open it in Project 2007 it will show work=0hrs;
duration=0days.
I tried to equalize the "Options" parameters in both machines, but the
problem is still there. Why?