T
tshad
I agree with you as long as you enter the Actual Start Date or use theJohn said:Tom,
Estimated dates become fixed when a task starts and finishes. The Start
and Finish fields in Project are dynamic - up to a point. That point
being reality. Once a task has actually started, the start date is no
longer an estimate. This emulates the real world so if that process does
play with what you want to do, then Project isn't the application you
want. Maybe what you really want are the baseline dates. Baseline dates
preserve the original plan so progress to the original plan can be
measured.
Resource Usage sheet, neither of which I use. Actually, SP2 fixed (I
believe) my problem where the only task that didn't change Start Date if you
add a task or change a duration was a task that had anything in the
%Completed column (if you have the task set to "as soon as possible").
Project splits the task now instead of depending on the previous task (if
that is how Precedence is set) which if set would also set that task. Now
all my tasks that are not set will get re-calculated. And any task that is
not 100% completed have their end date readjusted. This wasn't happening
before so I assume I am not the only one with this question.
I didn't. That was what was causing my problem. I actually like whatAs far as what date applies to the Gantt bar, well that depends on how
the bar styles are formatted (Format/Bar Styles). The default Gantt bar
format is for bars to start on the date in the Start field, which is the
estimated start date. However, as I said before, once the task actually
starts, Project adjusts the Start field to equal the Actual Start field.
Service Pack 2 (SP2) for Project 2003 was released to resolve several
glitches with the application. If you happen to like the way Project
2003 worked before SP2, then you are definitely not using Project as it
was designed so don't expect it to act the way you want.
Project is doing now. I was confused by when dates were fixed. Now %Work
Completed doesn't seem to do anything which was driving my crazy (as that
was what I was using before). But once I figured out that %Completed seemed
to do what %Work Completed used to do it is fine.
Thanks,
Tom