T
tshad
I have the following Summary Task and tasks.
12 Development 24.5 days 100% Tue 2/6/07 Tue 3/13/07
13 Create 3 days 100% Tue 2/6/07 Fri 2/9/07
14 Create 0.5 days 100% Fri 2/9/07 Mon 2/12/07 13
15 Create 2 days 100% Mon 2/12/07 Wed 2/14/07 14
16 Create 1 day 100% Wed 2/14/07 Thu 2/15/07 15
17 Create 2 days 100% Thu 2/15/07 Mon 2/19/07 16
18 Make 4 days 100% Mon 2/19/07 Fri 2/23/07 17
19 Create 1 day 100% Fri 2/23/07 Mon 2/26/07 18
20 Create 3 days 100% Mon 2/26/07 Thu 3/1/07 19
21 Create 0.5 days 100% Thu 3/1/07 Thu 3/1/07 20
22 Create 0.5 days 100% Thu 3/1/07 Fri 3/2/07
21
23 Create 0.5 days 100% Fri 3/2/07 Fri 3/2/07
22
24 Call 1 day 100% Fri 3/2/07 Mon 3/5/07
23
25 Create 0.5 days 0% Mon 3/5/07 Tue 3/6/07 24
26 Make 1 day 50% Tue 3/6/07 Wed 3/7/07 25
27 Allow 2 days 0% Wed 3/7/07 Fri 3/9/07
26
28 Clone 1 day 0% Fri 3/9/07 Mon 3/12/07
27
29 Add 1 day 0% Mon 3/12/07 Tue 3/13/07 28
How can I be 100% done in the Summary Task "Development"???
I did find that task 13-23 are showing as Complete. Task 24 does not show
Complete (no Check Mark in Left column).
What seems to be happening is that the tasks 24-26 were added later after I
had already started work on the project (added %Work Completed values). Not
sure if this is causing it or not, but it seems that is the case. Why would
the summary show as 100% when all the tasks that would show as completed
were completed. Obviously it isn't 100% complete.
Thanks,
Tom
12 Development 24.5 days 100% Tue 2/6/07 Tue 3/13/07
13 Create 3 days 100% Tue 2/6/07 Fri 2/9/07
14 Create 0.5 days 100% Fri 2/9/07 Mon 2/12/07 13
15 Create 2 days 100% Mon 2/12/07 Wed 2/14/07 14
16 Create 1 day 100% Wed 2/14/07 Thu 2/15/07 15
17 Create 2 days 100% Thu 2/15/07 Mon 2/19/07 16
18 Make 4 days 100% Mon 2/19/07 Fri 2/23/07 17
19 Create 1 day 100% Fri 2/23/07 Mon 2/26/07 18
20 Create 3 days 100% Mon 2/26/07 Thu 3/1/07 19
21 Create 0.5 days 100% Thu 3/1/07 Thu 3/1/07 20
22 Create 0.5 days 100% Thu 3/1/07 Fri 3/2/07
21
23 Create 0.5 days 100% Fri 3/2/07 Fri 3/2/07
22
24 Call 1 day 100% Fri 3/2/07 Mon 3/5/07
23
25 Create 0.5 days 0% Mon 3/5/07 Tue 3/6/07 24
26 Make 1 day 50% Tue 3/6/07 Wed 3/7/07 25
27 Allow 2 days 0% Wed 3/7/07 Fri 3/9/07
26
28 Clone 1 day 0% Fri 3/9/07 Mon 3/12/07
27
29 Add 1 day 0% Mon 3/12/07 Tue 3/13/07 28
How can I be 100% done in the Summary Task "Development"???
I did find that task 13-23 are showing as Complete. Task 24 does not show
Complete (no Check Mark in Left column).
What seems to be happening is that the tasks 24-26 were added later after I
had already started work on the project (added %Work Completed values). Not
sure if this is causing it or not, but it seems that is the case. Why would
the summary show as 100% when all the tasks that would show as completed
were completed. Obviously it isn't 100% complete.
Thanks,
Tom