N
Norma
When creating tasks that the dates are not consecutive, see example below.
We have Soccer Wall tasks that occur on 1 day on non-consecutive dates
thoughtout the start and end period. the start date is 1/5/07 and end is
02/26/07 and work is done for 16 days within the period but the header where
the tasks roll up reflects work being done for 37 days. Is there a way we
can have the header reflect that within the work span that work only occured
on 16 of the 37 days? hope this makes sense.
Soccer Walls 37 days Fri 1/5/07 Mon 2/06/07
"Put up soccer walls, 1 day Fri 1/5/07 Fri 1/5/07
Break down soccer 1 day Mon 1/8/07 Mon 1/08/07
"Put up soccer walls, 1 day Fri 1/12/07 Fri 1/12/07
We have Soccer Wall tasks that occur on 1 day on non-consecutive dates
thoughtout the start and end period. the start date is 1/5/07 and end is
02/26/07 and work is done for 16 days within the period but the header where
the tasks roll up reflects work being done for 37 days. Is there a way we
can have the header reflect that within the work span that work only occured
on 16 of the 37 days? hope this makes sense.
Soccer Walls 37 days Fri 1/5/07 Mon 2/06/07
"Put up soccer walls, 1 day Fri 1/5/07 Fri 1/5/07
Break down soccer 1 day Mon 1/8/07 Mon 1/08/07
"Put up soccer walls, 1 day Fri 1/12/07 Fri 1/12/07