A
Andre Bal
I have a bloking issue with a project file. IT is a detailed plan with many
tasks that take between 5-15 minutes duration. After analising my project, i
found that although several tasks take 5 minutes (listed in task
information), the gant chart bar displays about 1 hour.
Even stranger, if i remove the deprendency of such task, then the task
duration is still five minutes, however the bar will also change to 5 minutes.
What is the cause of this ?
I have found no clues whatsowever, and my project duration is not reliable
now.
All taks have fixed duration, effort drivven with NO resources used.
Please advise since my total leadtime is negatively affected (im am running
a large disaster recovery test that MUST be fitted within a weekend, so
durastion releability is Key.
tasks that take between 5-15 minutes duration. After analising my project, i
found that although several tasks take 5 minutes (listed in task
information), the gant chart bar displays about 1 hour.
Even stranger, if i remove the deprendency of such task, then the task
duration is still five minutes, however the bar will also change to 5 minutes.
What is the cause of this ?
I have found no clues whatsowever, and my project duration is not reliable
now.
All taks have fixed duration, effort drivven with NO resources used.
Please advise since my total leadtime is negatively affected (im am running
a large disaster recovery test that MUST be fitted within a weekend, so
durastion releability is Key.