I have MS Project 2002, can the Duration be changed to show seconds. I have
the need for a timing chart to be displayed in seconds. Is there and add on
feature that does this? Is there another program that does let you use
seconds?
 
J

John

nick@FM said:
I have MS Project 2002, can the Duration be changed to show seconds. I have
the need for a timing chart to be displayed in seconds. Is there and add on
feature that does this? Is there another program that does let you use
seconds?

nick,
Project will display time values to the nearest tenth minute, but that's
it. However, if you only have a timeline that needs to display seconds,
you could simply scale everything up to minutes. Just remember that any
duration values that display hours will not be correct.

I doubt there are scheduling applications that work down to seconds. You
might just want to use a spreadsheet instead.

John
Project MVP
 
J

Jim Aksel

1 minute is the smallest unit of measure. You can enter 1.1 minutes which is
66 seconds. Anything smaller than 60 seconds displays as 0 minutes.
--
If this post was helpful, please consider rating it.

Jim

Visit http://project.mvps.org/ for FAQs and more information
about Microsoft Project
 