B
Brooke
When I insert new tasks, the duration for the sub-task doesn't change to
incorporate the new duration/time.
I have the option set to duration in "days" however, when the duration is
calculated, it calculates it in decimals ex. 163.13 days. How do I fixe both
problems.
incorporate the new duration/time.
I have the option set to duration in "days" however, when the duration is
calculated, it calculates it in decimals ex. 163.13 days. How do I fixe both
problems.