S
Sherri
Hi there,
I'm hoping there's an easy solution to this problem...all of my project
schedules appear to have the same issue.
The problem: fixed duration tasks are increasing their duration when
changes are made to (seemingly) unrelated tasks.
Example: Task A has a duration of 10 days. MS project has changed the
duration to 12.38 days. When the duration is reduced back to 10 days, a
warning message appears saying that Task X has had its duration increased to
accomodate the change made to Task A. When I investigate what has happened to
Task X, usually the duration has increased (quite significantly), say from 10
days to 26 days. When Task X is returned to its 10 day duration, the same
warning message appears for a different task, and so the domino effect goes
through the project until I've exhausted all of the tasks.
As far as I can tell, none of these tasks are directly related to one
another and there is no logical reason for a change in duration of one task
to affect the duration of another.
To add to the misery, it doesn't always warn me that it's changing a
duration elsewhere in the project.
help - it's wreaking havoc on my completion dates.
Thanks. Sherri
I'm hoping there's an easy solution to this problem...all of my project
schedules appear to have the same issue.
The problem: fixed duration tasks are increasing their duration when
changes are made to (seemingly) unrelated tasks.
Example: Task A has a duration of 10 days. MS project has changed the
duration to 12.38 days. When the duration is reduced back to 10 days, a
warning message appears saying that Task X has had its duration increased to
accomodate the change made to Task A. When I investigate what has happened to
Task X, usually the duration has increased (quite significantly), say from 10
days to 26 days. When Task X is returned to its 10 day duration, the same
warning message appears for a different task, and so the domino effect goes
through the project until I've exhausted all of the tasks.
As far as I can tell, none of these tasks are directly related to one
another and there is no logical reason for a change in duration of one task
to affect the duration of another.
To add to the misery, it doesn't always warn me that it's changing a
duration elsewhere in the project.
help - it's wreaking havoc on my completion dates.
Thanks. Sherri