S
Steve C
What would cause a duration in a brand new project to calculate differently
for two different users?
A co-worker of mine likes to open a new project, enter a task, then manually
enter a Start and Finish date just to see the duration between the two dates.
He recently entered a Start date of 1/15/07 and a Finish date of 4/16/07.
His program calculates the duration as 65.81 days, while my program
calculates it as 66 days.
What might be causing this discrepancy? Thanks.
for two different users?
A co-worker of mine likes to open a new project, enter a task, then manually
enter a Start and Finish date just to see the duration between the two dates.
He recently entered a Start date of 1/15/07 and a Finish date of 4/16/07.
His program calculates the duration as 65.81 days, while my program
calculates it as 66 days.
What might be causing this discrepancy? Thanks.