D
DavidC
Hi,
I have a master project file with 11 inserted project files. I need a an
overview of the project. An overview task is often derived from stat dates
and finish dates in one or more of the inserted projects. Hence the overview
task may show the time from tendering one of the project functions through to
completing the construction. Hence the start date would be from the start of
tendering, and the finish date would be the end of construction. Thing is
though that the tasks where those dates can be found are not sequenced in the
particular project file, that allows a simple summary task to be used.
What I have done is to set a start task and finish task in the overview
file, then link those up to the relevant project file's task start or finish
date. Then to get a task showing the whole duration from start to finish, I
link the date fields using the paste special command. Using predecessor
successor does not give the desired result. Using the link function the task
will then calculate the duration overall and effectively give me the summary
task for the overview. This is working reasonably well, EXCEPT, I now notice
that the links formed using Paste special have disappeared meaning that I no
longer have a nice dynamically linked overview.
With the project in a major state of flux, having the dates dynamic is
imperative to ensure that the general trend for the project is being
monitored.
Is this a known issue of the links disappearing when used in a master
project file? or is there something missing in the set up?
Regards
DavidC
I have a master project file with 11 inserted project files. I need a an
overview of the project. An overview task is often derived from stat dates
and finish dates in one or more of the inserted projects. Hence the overview
task may show the time from tendering one of the project functions through to
completing the construction. Hence the start date would be from the start of
tendering, and the finish date would be the end of construction. Thing is
though that the tasks where those dates can be found are not sequenced in the
particular project file, that allows a simple summary task to be used.
What I have done is to set a start task and finish task in the overview
file, then link those up to the relevant project file's task start or finish
date. Then to get a task showing the whole duration from start to finish, I
link the date fields using the paste special command. Using predecessor
successor does not give the desired result. Using the link function the task
will then calculate the duration overall and effectively give me the summary
task for the overview. This is working reasonably well, EXCEPT, I now notice
that the links formed using Paste special have disappeared meaning that I no
longer have a nice dynamically linked overview.
With the project in a major state of flux, having the dates dynamic is
imperative to ensure that the general trend for the project is being
monitored.
Is this a known issue of the links disappearing when used in a master
project file? or is there something missing in the set up?
Regards
DavidC