L
liz217
I have two questions regarding earned value calculations in Microsoft
Project. Our actual costs are tracked separately from hours worked, so I
have unchecked the box "Actual costs are always calculated by Microsoft
Project." I will manually enter the costs at the end of the month. Our
actual costs will be provided by our accounting department.
1. I have set my project to calculate earned value using Baseline2 and %
Complete. We are tracking the project using actual work hours. I have
entered actual costs for January and actual work hours to date (through Feb.
18). No matter what I set the status date to, the BCWP is the same.
Shouldn't it be different for Jan. 31 vs. today since there has been work
done in February?
2. When I go to the task usage view to see the time-phased BCWS and
Baseline2 Cost, something odd is happening. On only a few of my tasks, when
I enter a cost for Baseline2, say $1400, the BCWS is $1400 for one or two
days and then goes back to $0. No other costs are showing for Baseline2 on
that task and I have my status date set to the end of the project. Is the
BCWS the accumulated Baseline cost? Why would it go to $0 after a value has
been entered in the baseline cost?
Any advice will help. I'm wondering if it would be easier to track the
earned value in an Excel file. We have specific costs (actual & budgeted)
that we need entered on specific dates and Project seems to want to calculate
everything.
Thanks,
Liz
Project. Our actual costs are tracked separately from hours worked, so I
have unchecked the box "Actual costs are always calculated by Microsoft
Project." I will manually enter the costs at the end of the month. Our
actual costs will be provided by our accounting department.
1. I have set my project to calculate earned value using Baseline2 and %
Complete. We are tracking the project using actual work hours. I have
entered actual costs for January and actual work hours to date (through Feb.
18). No matter what I set the status date to, the BCWP is the same.
Shouldn't it be different for Jan. 31 vs. today since there has been work
done in February?
2. When I go to the task usage view to see the time-phased BCWS and
Baseline2 Cost, something odd is happening. On only a few of my tasks, when
I enter a cost for Baseline2, say $1400, the BCWS is $1400 for one or two
days and then goes back to $0. No other costs are showing for Baseline2 on
that task and I have my status date set to the end of the project. Is the
BCWS the accumulated Baseline cost? Why would it go to $0 after a value has
been entered in the baseline cost?
Any advice will help. I'm wondering if it would be easier to track the
earned value in an Excel file. We have specific costs (actual & budgeted)
that we need entered on specific dates and Project seems to want to calculate
everything.
Thanks,
Liz