Earned Values are not calculated?

R

Roberto

Why does MS Project does not calculate the BCWS and BCWP values of my project
(the value is = 0)?

The tasks have values for duration, work and have resources assigned. I can
insert a progress, but only the EAC, CV and VAC values are calculated.

Any hint is welcome.
 
R

Roberto

Found the answer:
- BEFORE entering any progress it is important to:
- Assure that any resource has a usage cost > 0
- Create a baseline

Doing this after entering progress does not help.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top