G
GTS
We haven't started our project and the task calendars have all been turned
upside down. I'm in MP 2007.
In a nutshell, all the exception dates in all my task calendars have
changed. I had set up exception dates according to the times the tasks cannot
happen. Now I have new information that changes the restriction dates. (It's
a construction project and we can't drill during the times the wildlife are
nesting and lambing. We now have new information, therefore new restrictions.)
Do I just go into the task calendars and delete/rewrite the exception dates?
Or should I back up and do new task calendars, delete the old ones and apply
new ones?
How would you approach it? I don't want to mess it up!
upside down. I'm in MP 2007.
In a nutshell, all the exception dates in all my task calendars have
changed. I had set up exception dates according to the times the tasks cannot
happen. Now I have new information that changes the restriction dates. (It's
a construction project and we can't drill during the times the wildlife are
nesting and lambing. We now have new information, therefore new restrictions.)
Do I just go into the task calendars and delete/rewrite the exception dates?
Or should I back up and do new task calendars, delete the old ones and apply
new ones?
How would you approach it? I don't want to mess it up!