M
Mary Ann
I am using Project 98
I am trying to get my head round elapsed duration tasks. I understand that
with an elapsed duration task it is scheduled irrespective of the work
calendar, so e.g. a 5 day elapsed duration task would constitute 120 hours
work (5 x 24) and could be scheduled over a non-working weekend.
I have read that an elapsed duration task is automatically defined as fixed
duration. When I add / remove resources, the task duration and the task work
remain unaltered. It does therefore seem to act like a Fixed Duration,
Effort Driven task. But when I look at the Task Information it is shown as
Fixed Units, Effort Driven – is this a bug or am I missing something?
I am trying to get my head round elapsed duration tasks. I understand that
with an elapsed duration task it is scheduled irrespective of the work
calendar, so e.g. a 5 day elapsed duration task would constitute 120 hours
work (5 x 24) and could be scheduled over a non-working weekend.
I have read that an elapsed duration task is automatically defined as fixed
duration. When I add / remove resources, the task duration and the task work
remain unaltered. It does therefore seem to act like a Fixed Duration,
Effort Driven task. But when I look at the Task Information it is shown as
Fixed Units, Effort Driven – is this a bug or am I missing something?