End dates on Calendar

K

Kelly

I want to keep my project duration showing on the Gantt chart, but I only
want the end dates to show on the Calendar. Is there a way to do this?

Thanks,
Kelly
 
M

Mike Glen

Hi Kelly,

Welcome to this Microsoft Project newsgroup :)

If you mean you just want a point in time for each task to show in the
Calendar view, then this is not possible. You could create milestones for
each task and then just show those, but that seems a bit tedious.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials
 