D
David Bowen
Hi,
I am trying to use a couple of enterprise project cost fields. The first
field simply to store the to revenue to be earned by the poject and the
second to calculate the current average day rate taking into account all
work in the project. The calculation used in the second is:
[Enterprise Project Cost1]/([Work]/7.5)
However when this field is calculated it seems to be a factor out. Can
anyone assist me as to why the calculation does not give the correct answer
that I work out when performing the calculation myself? For example my
calculation would give the following answer:
65700/(1765.87/7.5) = 279.04
Yet project gives the following answer = 6.73.
Thanks,
David
I am trying to use a couple of enterprise project cost fields. The first
field simply to store the to revenue to be earned by the poject and the
second to calculate the current average day rate taking into account all
work in the project. The calculation used in the second is:
[Enterprise Project Cost1]/([Work]/7.5)
However when this field is calculated it seems to be a factor out. Can
anyone assist me as to why the calculation does not give the correct answer
that I work out when performing the calculation myself? For example my
calculation would give the following answer:
65700/(1765.87/7.5) = 279.04
Yet project gives the following answer = 6.73.
Thanks,
David