Can some one help me on how to get a report from the project, a report which
shows, date wise, estimated hours and date wise estimated perrcentage of work
completion.
 
M

Murali

Try view -> Reports and select the report type you want. Hope this helps.

Regards,
Murali
 
J

Jan De Messemaeker

Sorry, you can only SORT data on task or resource (main sort)
It is not possible to rank soldiers alphabetically, the tallest one in
front.
HTH
 
K

Krishna Mohan

Hi,

Suppose if i want only by task wise, is itpossible,

Regards,
Krishna Mohan
 
J

Jan De Messemaeker

OK!

Show Task Usage View
On the right ("yellow") side, right-click, select Detail Styles

One of the lines to show is Work
If you want to show the difference between work already done and work left
to do also show Av-ctual Work

As for the cumulative figures there are two fields available, I'm not sure
what will suit you most:

Cumulative % complete, but this will not show perecfentages beyond the
actual data;
Cumulative Work

Then you can print the view.

Hope this helps,
 