L
Lee
All,
I am an experienced PM and have been using Project for some time now.
However, I have never looked at the programming aspect of Project (Macro's,
VBA, etc) and I think I need to start as I now have a problem which I think
needs this knowledge. My problem is this: -
I have created a project plan in the usual way (adding tasks, indenting
tasks to create Summary tasks, etc) and a Resource Pool with internal and
external resources in it. The internal and external resources have different
hourly rates. I have also created a Custom Field (OK, I've dabbled a little!)
for the Resources which is a text field stating Internal or External,
depending upon their status. I have assigned these resources to all of the
tasks in my plan.
What I want to do is to create an Excel Spreadsheet that lists the
following: -
Row1:
Column1 - Phase Name (These are the level 2 Summary Tasks)
Column 2 - Number of hours of Internal Resource Usage for this Phase
Column 3 - Number of hours of External Resource Usage for this Phase
Column 4 - The total of Internal and External Hours for this Phase
Row2, 3, 4, etc:
The same as Row 1 but for the next Phase in the project.
I have no idea where to start to try and get this out. I have tried several
things but get nowhere. The summary tasks have no resources assigned to them
so I cannot just run a custom report (I think!) to get the info out I am
looking for.
Is this possible? Should I be thinking along the lines of VBA or Macros or
both?
Anyone who can shed some light on this for me would be greatly appreciated!
Kindest Regards
Lee
I am an experienced PM and have been using Project for some time now.
However, I have never looked at the programming aspect of Project (Macro's,
VBA, etc) and I think I need to start as I now have a problem which I think
needs this knowledge. My problem is this: -
I have created a project plan in the usual way (adding tasks, indenting
tasks to create Summary tasks, etc) and a Resource Pool with internal and
external resources in it. The internal and external resources have different
hourly rates. I have also created a Custom Field (OK, I've dabbled a little!)
for the Resources which is a text field stating Internal or External,
depending upon their status. I have assigned these resources to all of the
tasks in my plan.
What I want to do is to create an Excel Spreadsheet that lists the
following: -
Row1:
Column1 - Phase Name (These are the level 2 Summary Tasks)
Column 2 - Number of hours of Internal Resource Usage for this Phase
Column 3 - Number of hours of External Resource Usage for this Phase
Column 4 - The total of Internal and External Hours for this Phase
Row2, 3, 4, etc:
The same as Row 1 but for the next Phase in the project.
I have no idea where to start to try and get this out. I have tried several
things but get nowhere. The summary tasks have no resources assigned to them
so I cannot just run a custom report (I think!) to get the info out I am
looking for.
Is this possible? Should I be thinking along the lines of VBA or Macros or
both?
Anyone who can shed some light on this for me would be greatly appreciated!
Kindest Regards
Lee