Exporting Schedule Information

P

Philg

I have a challenge to communicate milestone status information to a large
organisation and client from a large number of independent schedules. I have
been asked to develop a routine to automatically extract data from MSP and
populate Excel. Is this a good idea? Would I be better considering an
interface into Access? Is this achievable without too much effort?

Thank you
 
M

Mike Glen

Hi Philg,

You will have to use vba to automate this. I thus suggest you try posting
on the developer newsgroup. Please see FAQ Item: 24. Project Newsgroups.
FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Mike Glen
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top