J
Jen B
I am using Project 2003 enterprise. I have 3 plans linked together, a
resource plan, vendor submitted plan, and master plan. However, it is not
appropriate to link to the vendor plan for submission to management. How do
I reflect the durations they expect and the review/revise cycles that belong
to our staff?
For example; they will write a guide and expect it to take 2 weeks, my staff
must review that guide within 5 days. How do I create a task for our review
designed to start at the end of the estimated 2 weeks without linking but
still showing a 2 weeks and 5 days timeline.
resource plan, vendor submitted plan, and master plan. However, it is not
appropriate to link to the vendor plan for submission to management. How do
I reflect the durations they expect and the review/revise cycles that belong
to our staff?
For example; they will write a guide and expect it to take 2 weeks, my staff
must review that guide within 5 days. How do I create a task for our review
designed to start at the end of the estimated 2 weeks without linking but
still showing a 2 weeks and 5 days timeline.