Filtered Calendars - Project 2003

V

VickiR

I'm trying to generate a calendar from an existing Gaant chart, using only
filtered tasks. I have not been able to generate a calendar without the
entire schedule appearing which resulting in multiple pages of "overflow".
Any suggestions would be greatly appreciated.
 
J

JulieS

Hello VickiR,

Have you applied the filter to the Calendar view? (Project > Filtered
For > More filters?) Which filter are you attempting to use?

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 