Simha
Hi all
I have a task which has a 24hrs as scheduled, let's say 03/01/06 - 03/03/06 ,
after putting actuals for 3 days, 1(-3 of Mar) the task is marked as 100%
done,
so far so good.
I realise that I need 1 more hr to actually finish the task, therefore I
enter 1hr in
"Remaining Work" field. I expect that the finish date should reflect the
next working day (03/06/06 Monday), I have checked my Proj.calendar, ,
resource calendar / Task Calendar,if it is marked as "nonworking time", and
ensured that it is a working day.
Here is the beginning of my problem, my finish date is unreasonable, instead
of
03/06/06 it shows 04/04/2006.
What else should I check to fix this problem.
Tons of thanks in advance
Simha
I have a task which has a 24hrs as scheduled, let's say 03/01/06 - 03/03/06 ,
after putting actuals for 3 days, 1(-3 of Mar) the task is marked as 100%
done,
so far so good.
I realise that I need 1 more hr to actually finish the task, therefore I
enter 1hr in
"Remaining Work" field. I expect that the finish date should reflect the
next working day (03/06/06 Monday), I have checked my Proj.calendar, ,
resource calendar / Task Calendar,if it is marked as "nonworking time", and
ensured that it is a working day.
Here is the beginning of my problem, my finish date is unreasonable, instead
of
03/06/06 it shows 04/04/2006.
What else should I check to fix this problem.
Tons of thanks in advance
Simha