Finish date problem

S

Simha

Hi all

I have a task which has a 24hrs as scheduled, let's say 03/01/06 - 03/03/06 ,
after putting actuals for 3 days, 1(-3 of Mar) the task is marked as 100%
done,
so far so good.

I realise that I need 1 more hr to actually finish the task, therefore I
enter 1hr in
"Remaining Work" field. I expect that the finish date should reflect the
next working day (03/06/06 Monday), I have checked my Proj.calendar, ,
resource calendar / Task Calendar,if it is marked as "nonworking time", and
ensured that it is a working day.

Here is the beginning of my problem, my finish date is unreasonable, instead
of
03/06/06 it shows 04/04/2006.

What else should I check to fix this problem.

Tons of thanks in advance

Simha
 
C

calihdog

Under Tools - Level Resources, do you have leveling calculations set to
automatic?
 
M

Mike Glen

Hi Simha,

Welcome to this Microsoft Project newsgroup :)

But is the 4 Mar marked as a working day in the calendar?

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 