S
Saviz
Hi,
Please advise:
I am unable to set a Correct Finish No Later Than constraint on a milestone
task.(No predecessor)
Scenario:
Date I want: Start:1/05/07 Finish 1/05/07
When I change the constraint to FNLT,the start date jumps to project start
date.
How can I specify a finish date and have a FNLT constraint applied on it?
Thanks,
Please advise:
I am unable to set a Correct Finish No Later Than constraint on a milestone
task.(No predecessor)
Scenario:
Date I want: Start:1/05/07 Finish 1/05/07
When I change the constraint to FNLT,the start date jumps to project start
date.
How can I specify a finish date and have a FNLT constraint applied on it?
Thanks,