S
scott.siegler
I have 3 tasks A, B, and C
Suppose:
Task A begins on Day 1
Task B ends on Day 10
Task C has a duration of 5 days. I want it to have a start to start
dependency with Task A, and a finish to finish dependency + 2 days with
B.
The problem is that Project is scheduling task C to end on Day 12 and
start on Day 7, even though it can potentially start on Day 1. I need
task C to be scheduled on Day 1 because I am going to have another task
with a start to start dependency with task C.
As I am new to Project, I was curious as to how you would model this in
Project to achieve my desired behavior.
Any help would be greatly appreciated.
Scott
Suppose:
Task A begins on Day 1
Task B ends on Day 10
Task C has a duration of 5 days. I want it to have a start to start
dependency with Task A, and a finish to finish dependency + 2 days with
B.
The problem is that Project is scheduling task C to end on Day 12 and
start on Day 7, even though it can potentially start on Day 1. I need
task C to be scheduled on Day 1 because I am going to have another task
with a start to start dependency with task C.
As I am new to Project, I was curious as to how you would model this in
Project to achieve my desired behavior.
Any help would be greatly appreciated.
Scott