B
Brian Lukanic
* Project 2003
* Task type: Fixed Work (and effort driven, as it has to be)
* Multiple resource assignments. Each resource's unit value is different.
* I have values entered for all elements (duration, work, units)
The problem:
* If I increase duration on the task, then the unit values decrease and a
Smart Tag is thrown. This works just as I would expect it to (I.E. it does
not change the fixed value.)
* But if I decrease duration on the task, the work decreases and keeps the
unit values fixed. It is almost as if Project is treating the task as Fixed
Units. But my task type is Fixed Work!!
Question:
* Why does Project fail to increase unit values when I decrease duration on
a Fixed Work task? Is it because Project is unable to make the call as to how
to re-rate the % values of each resource?
* why does Project not even give me a Smart Tag to help it decide?
* Task type: Fixed Work (and effort driven, as it has to be)
* Multiple resource assignments. Each resource's unit value is different.
* I have values entered for all elements (duration, work, units)
The problem:
* If I increase duration on the task, then the unit values decrease and a
Smart Tag is thrown. This works just as I would expect it to (I.E. it does
not change the fixed value.)
* But if I decrease duration on the task, the work decreases and keeps the
unit values fixed. It is almost as if Project is treating the task as Fixed
Units. But my task type is Fixed Work!!
Question:
* Why does Project fail to increase unit values when I decrease duration on
a Fixed Work task? Is it because Project is unable to make the call as to how
to re-rate the % values of each resource?
* why does Project not even give me a Smart Tag to help it decide?