M
Matt Goldencrown
Hi everyone. I'm trying to force the schedule of a task to stay the
same (Start and End dates stay the same i.e. Duration) while
increasing the amount of work assigned to a resource automatically.
What I mean is that I'd like to increase the number of labor hours (or
days etc.) that the task will require while keeping the duration
fixed. I know that there's a Fixed Duration setting, but when I
increase the amount of work the duration changes. I'm sure this is a
simple question, but I feel like I've tried everything. If I could
get two constraints, a Must Start On and a Must Finish On, the goal
would be accomplished, but that's not possible, correct?
Thanks,
Matt
same (Start and End dates stay the same i.e. Duration) while
increasing the amount of work assigned to a resource automatically.
What I mean is that I'd like to increase the number of labor hours (or
days etc.) that the task will require while keeping the duration
fixed. I know that there's a Fixed Duration setting, but when I
increase the amount of work the duration changes. I'm sure this is a
simple question, but I feel like I've tried everything. If I could
get two constraints, a Must Start On and a Must Finish On, the goal
would be accomplished, but that's not possible, correct?
Thanks,
Matt