I have a gantt chart that I would like to use for weekly status meeting
progress of my project.

When I go to Format-Bar Styles and when name = progress I can choose text to
place under my bar of "% Complete" or "% Work Complete".

What is the definition of what each of these will provide when used with my
gantt chart?
 
M

Mike Glen

Hi dsm,

Welcome to this Microsoft Project newsgroup :)

%Complete relates to the passing of time, or % Duration complete. If you
have a Duration of 10 days for a task that will take 80 man-hours of work
and you are at the end of day 5, then the task is 50%
complete. However, if you have only done 20 man-hours of work, then % Work
Complete is 25%.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 
M

Mike Glen

Hi DSM,

As I said in my email: please use the newsgroups - there are others more
expert than I out there and you could well get better or different advice.
Also, responses may help others. :)

Mike Glen
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top