thanks ...
Well...i think my question was a little bit out, i wasn`t thinking that
anyone could give me an answer with 2 or 3 lines...i was trying to know if
there was any tutorials that i could study from. I will explore the help menu
and try to run some more tests...i hope you help me in the next question...
I`m sorry, but my english is a little bit stucked ...
see you soon...and thanks a lot again
Rita
:
That is a pretty big question. You can read about the "return type" for each
custom field by inserting the column and then hovering over it. For example,
if you insert Date1 and then hover over it, you get a choice "Help on
Date1".. If you open that hyperlink, it will tell you about the return
types, etc.
One thing to note, dates in Project are of type Variant, not "Date" ....
same with duration. So when you look at a formula such as "ProjDateDiff" it
is exepcting something that evaluates to "Date" instead of "Variant" or
"Object". In your specific case, BaselineFinish3 might have the value NA
which is not of type date.
See my other post for a different procedure.
--
If this post was helpful, please consider rating it.
Jim Aksel, MVP
Check out my blog for more information:
http://www.msprojectblog.com
:
Thanks
It`s working now...It seems that i have to use a special function to do the
diffrence between dates, and give me back a duration (ProjDateValue)
Could someone give me the instructions to use the right functions in the
right custom fields types? Because i had already tried the function DateDiff
(wich i think would give the difference with date units), and it didn`t work
out.
thanks a lot
Rita
:
Try a duration field with the following formula:
IIf([Baseline3 Finish]=ProjDateValue('NA'),0,ProjDateDiff([Baseline3 Finish],[Early
Finish]))
That will display "0" if the Baseline3 Finish field is blank.
- Andrew Lavinsky
Blog:
http://blogs.catapultsystems.com/epm
Hi everyone...
This is probably real simple for you, but i think i`m loosing to much
time
looking for the answer!
I`m trying to do a simple custom field with a formula, that gives me
the
finish variance [Early Finish]-[Baseline3 Finish], i have tried to use
finish
custom field type, the date and even the duration type...it keeps
given me
ERROR...could someone help me with this?
Thanks,
Rita
.