Ignbell --
Work - Baseline Work = Work Variance
Therefore, put the following formula in a Number field:
[Work Variance]/[Baseline Work]
This will reveal your % of Work that is over or under its original Baseline
budget. For example, I baselined a task at 40 hours of Work (Baseline Work
= 40h). Currently, the Work = 48 hours. Therefore:
Work Variance = Work - Baseline Work
Work Variance = 48 - 40
Work Variance = 8
% Over Budget = 8/40 = .20
You will see the .20 in the Number field. If you want the percent sign to
show up in the result, then you need to use the following formula in a Text
field instead:
([Work Variance]/[Baseline Work] * 100) & "%"
Hope this helps.
Ignbell said:
Hi, i need a formula that shows me the result in % but i don´t know how to
do
it. my formula is:
([Trabalho]-[Trabalho do Plano Base])/[Trabalho do Plano Base]
Trabalho means Work
Thanks!