M
MaryK
Hi,
Is it possible for MS Project to create additional column (Total Duration)
that would perform a calculation:
Qty column * Duration (per Unit) in minutes column = Total Duration (per
Lot) in minutes
Example:
Qty Duration/Unit Duration/Lot
10 2.6m 26m
1 5m 5m
Presently I have to remember to manually calculate qty * duration time per
unit, so I can enter the duration per lot. Example:
Qty Duration
10 26m
1 5m
Your help will be greatly appreciated,
Mary
Is it possible for MS Project to create additional column (Total Duration)
that would perform a calculation:
Qty column * Duration (per Unit) in minutes column = Total Duration (per
Lot) in minutes
Example:
Qty Duration/Unit Duration/Lot
10 2.6m 26m
1 5m 5m
Presently I have to remember to manually calculate qty * duration time per
unit, so I can enter the duration per lot. Example:
Qty Duration
10 26m
1 5m
Your help will be greatly appreciated,
Mary