Real task duration

D

Danny_dH

Hello,

I'm a total Project Noob. I'm using Project 2007 and I want to do a
'simple'? task.

I have a main project (MAIN). Then I have a sub project (indent 1)(SUB).
This sub has 2 subprojects (indent 2) (SUB1 - SUB2).
So it looks like this:
MAIN start: 01/01 - end: 03/01
dur: 3 days
SUB start: 01/01 - end: 03/01
dur: 3 days
SUB1 start: 01/01 - end: 01/01
dur: 1day
SUB2 start: 03/01 - end: 03/01
dur: 1day

Now, that Projects says that the duration is 3 days.. ok.. I can live with
that, but then I add a column named actual duration.. and that one does the
same.
When I now add a column 'Actual Work', it tells me SUB1: 8h, SUB2: 8h, SUB:
16h, MAIN: 16h.... so this column does a correct calculation.

Now how can I add a column, which gives me the correct REAL sum of workdays,
so one that says 2 days... I just want to have this overview to calculate my
total number of spent workdays.

Sorry if this is a stupidly simple question, but.. I don't seem to be able
to find it.

Any help should be appreciated.
 
J

JulieS

Hello Danny_dH,

Hmm. Well something does seem off. Jan 1 in 2010 was a Friday.
Jan 3 was a Sunday. Have you changed your calendar to allow
working on weekends? Okay, so assuming you've allowed 7 working
days -- that does work. But if you've changed your calendar, then
it *is* 3 working days.

Actual Duration is used when tracking, and unless the project has
been tracked, Actual Duration should be zero.

So, let's start over. What is your calendar definition? What
are your working days?

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 
D

Danny_dH

Hello Julie,

sorry bout the bad choice of date: I acutally ment 3 following days:

better example:
Mon 4 jan > Wed 6 Jan
I am using the standard calendar, meaning, Mon-Fri, 8.00 > 12.00, 13.00 >
17.00
The rest of my situation stays the same.. so I hope this is more clear..

sorry bout the misunderstanding.
Danny
 
J

JulieS

Thanks for the clarification, Danny. That helps.

The summary (Main in your example) calculation is correct. If
one of the subproject's total duration is 3 days, then the
summary duration is 3 days. I don't understand how you expect it
to show 2 workdays if it starts on Monday and ends at the end of
the day on Wednesday. Is that not 3 days?

I think the issue is in your interpretation of duration. It is
*not* "man hours". If you'd like to see man hours, the correct
field is Work. You may display work in days if that helps. See
Tools > Options, Schedule tab -- "Work is entered in" setting.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 
D

Danny_dH

Hey Julie,

well.. it is as you say: my idea of worked days/hours is different then what
project does with it..

My idea was that, when choosing the column 'actual duration', project should
calculate everything in days.

I now changed the "Work is entered in" to days.. and now calculation is
fine in days.. but I cannot enter hours anymore..

maybe I want to much of it ;)
Is there a way to have both?

Thanks for helping me out Julie :)
 
S

Steve House

FYI - Project calculates EVERYTHING in units of minutes to the nearest 10th.
All other units are just there for user convenience and are always converted
into minutes internally for calculation. Actual duration is that amount of
time that has passed during which work has or could have taken place
according to the calendar since the task began. Duration (ie, total
duration) = Actual Duration + Remaining Duration. Work is the amount of
actual activity that has taken place. A painter starts Mon at 8am and
spends an hour applying a primer coat which has to dry overnight. He comes
back Tues and does a second primer coat, also taking an hour. Then Wed he
spends an hour on a first colour coat, letting it dry overnight. Thur he
spends an hour doing the second colour coat.. Then Fri he comes in for all
day doing all the fine detail and cleanup. Before work begins the plan
states that Duration is 40 hours and Work is 12 man-hours. Thursday
evening at 5pm we update progress and everything has happened exactly as
planned. Actual Duration to the status point is 32 hours, Remaining
Duration is 8 hours. Actual Work to the status point is 4 man-hours,
Remaining Work is 8 hours. % Complete is 32/40 or 80%. % Work Complete is
4/12 or 33%.
 
J

JulieS

You're welcome, Danny. You can enter work or duration in
whatever time unit you want, ranging from minutes to months.
Just include the unit measurement as you key enter data.

Use:
m for minutes
h for hours
d for days
w for weeks
mo for months

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 
T

tom_willpa

high quality Soccer jerseys NBA Jersey tracksuit and jackets, GHD
hairstraightener supplier from www.willpa.com

Are you a Retail businessman who bother by the purchase price? China
Cheapest TOP wholesale website can help you

we are specialize in replica sport goods manufacturing in china, we can
offer you all kinds of soccer jersey, NBA jersey,shoes and so on. they are
the best brand replica goods whih are look the same as the original goods.
excellent quality and steady supply for them. we have been marketed in Europe
and American for 3 year. all the goods we offer are AAA quality. our soccer
jersey are Thailand style. If any goods you buy from my company have problem,
we will refund or resend them again. Most of ourProducts have no minimum
order requirements,soyou can shop retail goods at wholesale prices. if you
can buy more than 300usd. We offer free shipping. The more you buy the more
discount for you.

National soccer jerseys: http://www.willpa.com
Club soccer jerseys: http://www.willpa.com
NBA Jerseys: http://www.willpa.com
T-shirt and shirt: http://www.willpa.com
Tracksuit: http://www.willpa.com
Hoody & Jackets: http://www.willpa.com
UGG boots: http://www.willpa.com
Hair style: http://www.willpa.com
shopping Index: http://www.willpa.com

EMS shipping. 7days arrive, paypal accept

want more information pls contact us or check our website: www.willpa.com
 
D

Danny_dH

Hey both,

just a general reply then: since the actual calculation I want is not
something project does by default:

is it possible to have both actual work in hours and days?

I know have set the following

Day1: 8hours
Day2: - nothing
Day3: 8hours

And the column Actual Work gives me 16 hours, which is fine, but I now want
an additional column that converts this hours > days..

possible?

thanks a lot.
bR
Danny
 
R

Rob Schneider

[Actual Work] will be stored in Project in Minutes. You could make a
new Number custom field called [Actual Work Hours] and make it equal to
the formula [Actual Work]/60 where the 60 converts minutes into hours.
this work for your needs?

--rms

www.rmschneider.com
 
D

Danny_dH

Hey Rob,

this more or less does what it needs to..
I know have the column Actual Work, which states x hours/task and x
hours/total job, I added a custom column (days worked), which weirdly enough
contains just [Actual Work] and displays the real amount of days worked (so
8hours in the column Actual work displays 1 day in the days worked column.
Which is fine and as it should be..
But then it show the sum (in this case, all the tasks add up to 51 hours in
the Actual work column) but it doesn't show the sum for the days worked
column.. it just states 0 days.

Sorry if I'm being obsessive about this, but I want to get it
straightforward and easy to use :)


Rob Schneider said:
[Actual Work] will be stored in Project in Minutes. You could make a
new Number custom field called [Actual Work Hours] and make it equal to
the formula [Actual Work]/60 where the 60 converts minutes into hours.
this work for your needs?

--rms

www.rmschneider.com




Hey both,

just a general reply then: since the actual calculation I want is not
something project does by default:

is it possible to have both actual work in hours and days?

I know have set the following

Day1: 8hours
Day2: - nothing
Day3: 8hours

And the column Actual Work gives me 16 hours, which is fine, but I now want
an additional column that converts this hours> days..

possible?

thanks a lot.
bR
Danny
.
 
R

Rob Schneider

Danny_dH,

Sorry ... I don't quite understand. Can you reframe the question? My
hunch is that what you want/need to do should be able to be handled by
Project without the need of all these special fields. What are you
trying to do?

In any event, to get the sums of custom field [Days Worked] in the
summary rows, did you notice the control for that on the custom field
dialogue box?


--rms

www.rmschneider.com




Hey Rob,

this more or less does what it needs to..
I know have the column Actual Work, which states x hours/task and x
hours/total job, I added a custom column (days worked), which weirdly enough
contains just [Actual Work] and displays the real amount of days worked (so
8hours in the column Actual work displays 1 day in the days worked column.
Which is fine and as it should be..
But then it show the sum (in this case, all the tasks add up to 51 hours in
the Actual work column) but it doesn't show the sum for the days worked
column.. it just states 0 days.

Sorry if I'm being obsessive about this, but I want to get it
straightforward and easy to use :)


Rob Schneider said:
[Actual Work] will be stored in Project in Minutes. You could make a
new Number custom field called [Actual Work Hours] and make it equal to
the formula [Actual Work]/60 where the 60 converts minutes into hours.
this work for your needs?

--rms

www.rmschneider.com




Hey both,

just a general reply then: since the actual calculation I want is not
something project does by default:

is it possible to have both actual work in hours and days?

I know have set the following

Day1: 8hours
Day2: - nothing
Day3: 8hours

And the column Actual Work gives me 16 hours, which is fine, but I now want
an additional column that converts this hours> days..

possible?

thanks a lot.
bR
Danny

:

You're welcome, Danny. You can enter work or duration in
whatever time unit you want, ranging from minutes to months.
Just include the unit measurement as you key enter data.

Use:
m for minutes
h for hours
d for days
w for weeks
mo for months

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project

On 5/7/2010 4:15 PM, Danny_dH wrote:
Hey Julie,

well.. it is as you say: my idea of worked days/hours is different then what
project does with it..

My idea was that, when choosing the column 'actual duration', project should
calculate everything in days.

I now changed the "Work is entered in" to days.. and now calculation is
fine in days.. but I cannot enter hours anymore..

maybe I want to much of it ;)
Is there a way to have both?

Thanks for helping me out Julie :)



:

Thanks for the clarification, Danny. That helps.

The summary (Main in your example) calculation is correct. If
one of the subproject's total duration is 3 days, then the
summary duration is 3 days. I don't understand how you expect it
to show 2 workdays if it starts on Monday and ends at the end of
the day on Wednesday. Is that not 3 days?

I think the issue is in your interpretation of duration. It is
*not* "man hours". If you'd like to see man hours, the correct
field is Work. You may display work in days if that helps. See
Tools> Options, Schedule tab -- "Work is entered in" setting.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project

On 5/7/2010 3:52 AM, Danny_dH wrote:
Hello Julie,

sorry bout the bad choice of date: I acutally ment 3 following days:

better example:
Mon 4 jan> Wed 6 Jan
I am using the standard calendar, meaning, Mon-Fri, 8.00> 12.00, 13.00>
17.00
The rest of my situation stays the same.. so I hope this is more clear..

sorry bout the misunderstanding.
Danny

:

Hello,

I'm a total Project Noob. I'm using Project 2007 and I want to do a
'simple'? task.

I have a main project (MAIN). Then I have a sub project (indent 1)(SUB).
This sub has 2 subprojects (indent 2) (SUB1 - SUB2).
So it looks like this:
MAIN start: 01/01 - end: 03/01
dur: 3 days
SUB start: 01/01 - end: 03/01
dur: 3 days
SUB1 start: 01/01 - end: 01/01
dur: 1day
SUB2 start: 03/01 - end: 03/01
dur: 1day

Now, that Projects says that the duration is 3 days.. ok.. I can live with
that, but then I add a column named actual duration.. and that one does the
same.
When I now add a column 'Actual Work', it tells me SUB1: 8h, SUB2: 8h, SUB:
16h, MAIN: 16h.... so this column does a correct calculation.

Now how can I add a column, which gives me the correct REAL sum of workdays,
so one that says 2 days... I just want to have this overview to calculate my
total number of spent workdays.

Sorry if this is a stupidly simple question, but.. I don't seem to be able
to find it.

Any help should be appreciated.
.

.
.
 
S

Steve House

Go to Tools Customize Fields where you created the Days Worked column and
make sure it's set to rollup to summaries
--
Steve House
MS Project Trainer & Consultant

Danny_dH said:
Hey Rob,

this more or less does what it needs to..
I know have the column Actual Work, which states x hours/task and x
hours/total job, I added a custom column (days worked), which weirdly
enough
contains just [Actual Work] and displays the real amount of days worked
(so
8hours in the column Actual work displays 1 day in the days worked column.
Which is fine and as it should be..
But then it show the sum (in this case, all the tasks add up to 51 hours
in
the Actual work column) but it doesn't show the sum for the days worked
column.. it just states 0 days.

Sorry if I'm being obsessive about this, but I want to get it
straightforward and easy to use :)


Rob Schneider said:
[Actual Work] will be stored in Project in Minutes. You could make a
new Number custom field called [Actual Work Hours] and make it equal to
the formula [Actual Work]/60 where the 60 converts minutes into hours.
this work for your needs?

--rms

www.rmschneider.com




Hey both,

just a general reply then: since the actual calculation I want is not
something project does by default:

is it possible to have both actual work in hours and days?

I know have set the following

Day1: 8hours
Day2: - nothing
Day3: 8hours

And the column Actual Work gives me 16 hours, which is fine, but I now
want
an additional column that converts this hours> days..

possible?

thanks a lot.
bR
Danny

:

You're welcome, Danny. You can enter work or duration in
whatever time unit you want, ranging from minutes to months.
Just include the unit measurement as you key enter data.

Use:
m for minutes
h for hours
d for days
w for weeks
mo for months

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project

On 5/7/2010 4:15 PM, Danny_dH wrote:
Hey Julie,

well.. it is as you say: my idea of worked days/hours is different
then what
project does with it..

My idea was that, when choosing the column 'actual duration', project
should
calculate everything in days.

I now changed the "Work is entered in" to days.. and now calculation
is
fine in days.. but I cannot enter hours anymore..

maybe I want to much of it ;)
Is there a way to have both?

Thanks for helping me out Julie :)



:

Thanks for the clarification, Danny. That helps.

The summary (Main in your example) calculation is correct. If
one of the subproject's total duration is 3 days, then the
summary duration is 3 days. I don't understand how you expect it
to show 2 workdays if it starts on Monday and ends at the end of
the day on Wednesday. Is that not 3 days?

I think the issue is in your interpretation of duration. It is
*not* "man hours". If you'd like to see man hours, the correct
field is Work. You may display work in days if that helps. See
Tools> Options, Schedule tab -- "Work is entered in" setting.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project

On 5/7/2010 3:52 AM, Danny_dH wrote:
Hello Julie,

sorry bout the bad choice of date: I acutally ment 3 following
days:

better example:
Mon 4 jan> Wed 6 Jan
I am using the standard calendar, meaning, Mon-Fri, 8.00> 12.00,
13.00>
17.00
The rest of my situation stays the same.. so I hope this is more
clear..

sorry bout the misunderstanding.
Danny

:

Hello,

I'm a total Project Noob. I'm using Project 2007 and I want to do
a
'simple'? task.

I have a main project (MAIN). Then I have a sub project (indent
1)(SUB).
This sub has 2 subprojects (indent 2) (SUB1 - SUB2).
So it looks like this:
MAIN start: 01/01 - end: 03/01
dur: 3 days
SUB start: 01/01 - end:
03/01
dur: 3 days
SUB1 start: 01/01 - end:
01/01
dur: 1day
SUB2 start: 03/01 - end:
03/01
dur: 1day

Now, that Projects says that the duration is 3 days.. ok.. I can
live with
that, but then I add a column named actual duration.. and that one
does the
same.
When I now add a column 'Actual Work', it tells me SUB1: 8h, SUB2:
8h, SUB:
16h, MAIN: 16h.... so this column does a correct calculation.

Now how can I add a column, which gives me the correct REAL sum of
workdays,
so one that says 2 days... I just want to have this overview to
calculate my
total number of spent workdays.

Sorry if this is a stupidly simple question, but.. I don't seem to
be able
to find it.

Any help should be appreciated.
.

.
.
 
D

Danny_dH

WOOHOOO that's IT!!!! Finally got my total days worked sum :)

GREAT GREAT..

Thanks everyone for contributing!!!

Steve House said:
Go to Tools Customize Fields where you created the Days Worked column and
make sure it's set to rollup to summaries
--
Steve House
MS Project Trainer & Consultant

Danny_dH said:
Hey Rob,

this more or less does what it needs to..
I know have the column Actual Work, which states x hours/task and x
hours/total job, I added a custom column (days worked), which weirdly
enough
contains just [Actual Work] and displays the real amount of days worked
(so
8hours in the column Actual work displays 1 day in the days worked column.
Which is fine and as it should be..
But then it show the sum (in this case, all the tasks add up to 51 hours
in
the Actual work column) but it doesn't show the sum for the days worked
column.. it just states 0 days.

Sorry if I'm being obsessive about this, but I want to get it
straightforward and easy to use :)


Rob Schneider said:
[Actual Work] will be stored in Project in Minutes. You could make a
new Number custom field called [Actual Work Hours] and make it equal to
the formula [Actual Work]/60 where the 60 converts minutes into hours.
this work for your needs?

--rms

www.rmschneider.com




On 12/05/10 14:26, Danny_dH wrote:
Hey both,

just a general reply then: since the actual calculation I want is not
something project does by default:

is it possible to have both actual work in hours and days?

I know have set the following

Day1: 8hours
Day2: - nothing
Day3: 8hours

And the column Actual Work gives me 16 hours, which is fine, but I now
want
an additional column that converts this hours> days..

possible?

thanks a lot.
bR
Danny

:

You're welcome, Danny. You can enter work or duration in
whatever time unit you want, ranging from minutes to months.
Just include the unit measurement as you key enter data.

Use:
m for minutes
h for hours
d for days
w for weeks
mo for months

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project

On 5/7/2010 4:15 PM, Danny_dH wrote:
Hey Julie,

well.. it is as you say: my idea of worked days/hours is different
then what
project does with it..

My idea was that, when choosing the column 'actual duration', project
should
calculate everything in days.

I now changed the "Work is entered in" to days.. and now calculation
is
fine in days.. but I cannot enter hours anymore..

maybe I want to much of it ;)
Is there a way to have both?

Thanks for helping me out Julie :)



:

Thanks for the clarification, Danny. That helps.

The summary (Main in your example) calculation is correct. If
one of the subproject's total duration is 3 days, then the
summary duration is 3 days. I don't understand how you expect it
to show 2 workdays if it starts on Monday and ends at the end of
the day on Wednesday. Is that not 3 days?

I think the issue is in your interpretation of duration. It is
*not* "man hours". If you'd like to see man hours, the correct
field is Work. You may display work in days if that helps. See
Tools> Options, Schedule tab -- "Work is entered in" setting.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project

On 5/7/2010 3:52 AM, Danny_dH wrote:
Hello Julie,

sorry bout the bad choice of date: I acutally ment 3 following
days:

better example:
Mon 4 jan> Wed 6 Jan
I am using the standard calendar, meaning, Mon-Fri, 8.00> 12.00,
13.00>
17.00
The rest of my situation stays the same.. so I hope this is more
clear..

sorry bout the misunderstanding.
Danny

:

Hello,

I'm a total Project Noob. I'm using Project 2007 and I want to do
a
'simple'? task.

I have a main project (MAIN). Then I have a sub project (indent
1)(SUB).
This sub has 2 subprojects (indent 2) (SUB1 - SUB2).
So it looks like this:
MAIN start: 01/01 - end: 03/01
dur: 3 days
SUB start: 01/01 - end:
03/01
dur: 3 days
SUB1 start: 01/01 - end:
01/01
dur: 1day
SUB2 start: 03/01 - end:
03/01
dur: 1day

Now, that Projects says that the duration is 3 days.. ok.. I can
live with
that, but then I add a column named actual duration.. and that one
does the
same.
When I now add a column 'Actual Work', it tells me SUB1: 8h, SUB2:
8h, SUB:
16h, MAIN: 16h.... so this column does a correct calculation.

Now how can I add a column, which gives me the correct REAL sum of
workdays,
so one that says 2 days... I just want to have this overview to
calculate my
total number of spent workdays.

Sorry if this is a stupidly simple question, but.. I don't seem to
be able
to find it.

Any help should be appreciated.
.

.

.

.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top