D
Danny_dH
Hello,
I'm a total Project Noob. I'm using Project 2007 and I want to do a
'simple'? task.
I have a main project (MAIN). Then I have a sub project (indent 1)(SUB).
This sub has 2 subprojects (indent 2) (SUB1 - SUB2).
So it looks like this:
MAIN start: 01/01 - end: 03/01
dur: 3 days
SUB start: 01/01 - end: 03/01
dur: 3 days
SUB1 start: 01/01 - end: 01/01
dur: 1day
SUB2 start: 03/01 - end: 03/01
dur: 1day
Now, that Projects says that the duration is 3 days.. ok.. I can live with
that, but then I add a column named actual duration.. and that one does the
same.
When I now add a column 'Actual Work', it tells me SUB1: 8h, SUB2: 8h, SUB:
16h, MAIN: 16h.... so this column does a correct calculation.
Now how can I add a column, which gives me the correct REAL sum of workdays,
so one that says 2 days... I just want to have this overview to calculate my
total number of spent workdays.
Sorry if this is a stupidly simple question, but.. I don't seem to be able
to find it.
Any help should be appreciated.
I'm a total Project Noob. I'm using Project 2007 and I want to do a
'simple'? task.
I have a main project (MAIN). Then I have a sub project (indent 1)(SUB).
This sub has 2 subprojects (indent 2) (SUB1 - SUB2).
So it looks like this:
MAIN start: 01/01 - end: 03/01
dur: 3 days
SUB start: 01/01 - end: 03/01
dur: 3 days
SUB1 start: 01/01 - end: 01/01
dur: 1day
SUB2 start: 03/01 - end: 03/01
dur: 1day
Now, that Projects says that the duration is 3 days.. ok.. I can live with
that, but then I add a column named actual duration.. and that one does the
same.
When I now add a column 'Actual Work', it tells me SUB1: 8h, SUB2: 8h, SUB:
16h, MAIN: 16h.... so this column does a correct calculation.
Now how can I add a column, which gives me the correct REAL sum of workdays,
so one that says 2 days... I just want to have this overview to calculate my
total number of spent workdays.
Sorry if this is a stupidly simple question, but.. I don't seem to be able
to find it.
Any help should be appreciated.