B
Bill Yule
Where does actual duration come from?
And forget the formula: % Cmplt = (Act-Dur/Dur)*100!!!!
MSProject 2003. We use fixed duration, not effort driven tasks. The status
date for the project is 06/03/07. There is one holiday in the time period
discussed, 05/28/07 with an 8 hour day, 5 days a week calendar. The
engineers input their time, daily, to SAP and weekly we run a SQL to offload
their time for input to MSProject which is entered by hand (for now).
There is a task that shows:
% complete = 50, actual duration = 7.45, duration 49.25, remaining duration
= 7.45, start = 03/26/07, baseline duration = 10, baseline start = 05/03/07.
I’ve checked the Task Usage view and it agrees that time has been entered
against the task for 49 days, starting 03/26/07. Where does an Act Dur of
7.45 come from
And here is another one
% complete = 12, actual duration = 2.75, duration = 55.95, remaining
duration = 53.2, start = 03/26/07, baseline duration = 5, baseline start =
05/29/07.
I’ve checked the Task Usage view and found that it does not agree with
either actual duration or duration, time was entered for 49 days from
03/26/07 to 06/01/07.
Anyone have a clue where Actual Duration comes from?
And forget the formula: % Cmplt = (Act-Dur/Dur)*100!!!!
MSProject 2003. We use fixed duration, not effort driven tasks. The status
date for the project is 06/03/07. There is one holiday in the time period
discussed, 05/28/07 with an 8 hour day, 5 days a week calendar. The
engineers input their time, daily, to SAP and weekly we run a SQL to offload
their time for input to MSProject which is entered by hand (for now).
There is a task that shows:
% complete = 50, actual duration = 7.45, duration 49.25, remaining duration
= 7.45, start = 03/26/07, baseline duration = 10, baseline start = 05/03/07.
I’ve checked the Task Usage view and it agrees that time has been entered
against the task for 49 days, starting 03/26/07. Where does an Act Dur of
7.45 come from
And here is another one
% complete = 12, actual duration = 2.75, duration = 55.95, remaining
duration = 53.2, start = 03/26/07, baseline duration = 5, baseline start =
05/29/07.
I’ve checked the Task Usage view and found that it does not agree with
either actual duration or duration, time was entered for 49 days from
03/26/07 to 06/01/07.
Anyone have a clue where Actual Duration comes from?