Freezing progress lines

O

opilgaard

Hello group,

If you ad a new progress line and update the % complete then it also
effects any previous progress line.

Is there a way to avoid this, to freeze the old progress lines, so you
could visualise the development of the project over time?

If you have multiple frozen progress lines at some interval, this could
help you realise if a specific task gets more and more delayed or vice
versa. It would be a visual approach to recognising trouble areas.
 
G

Gérard Ducouret

Hello,
Tools / Tracking / Progress lines...
- Always display current progress line
- At projet status date
- Display at reccurring intervals
- Weely (for example)
- Every : Friday.....

Gérard Ducouret
 
O

opilgaard

Thank you for the quick answer!

This is definitely the function that I was looking for.

I noticed that if I enter a % completed and decide that it was wrong,
if I then enter a new % it doesn't change the current progress line
correspondingly. On the other hand, if I enter a progress of 0 or 100%
and then decide it was wrong & enter a new % it may effect the older
lines which were supposed to be frozen.

Hope this makes sense and you can help me on these minor details as
well.

Regards,

Ole
 