If you ad a new progress line and update the % complete then it also
effects any previous progress line.
Is there a way to avoid this, to freeze the old progress lines, so you
could visualise the development of the project over time?
If you have multiple frozen progress lines at some interval, this could
help you realise if a specific task gets more and more delayed or vice
versa. It would be a visual approach to recognising trouble areas.