Hi,
I have a small querry, When I open the pogress line dialogue box, it has got
options for displaying progress lines in relation to Actual Plan & Baseline
Plan.
Firstly, I dont understand what is "Actual plan" and secondly when I choose
the Baseline plan option, nothing shown I just see a straight line on status
date. I would like to tell you that my programme has been baselined &
resourced. Moreover by choosing Actual Plan I am able to see the cross line
for delayed activities.
Any comments would be appreciated.
I have a small querry, When I open the pogress line dialogue box, it has got
options for displaying progress lines in relation to Actual Plan & Baseline
Plan.
Firstly, I dont understand what is "Actual plan" and secondly when I choose
the Baseline plan option, nothing shown I just see a straight line on status
date. I would like to tell you that my programme has been baselined &
resourced. Moreover by choosing Actual Plan I am able to see the cross line
for delayed activities.
Any comments would be appreciated.