Presenting progress problem

P

Peters

Hello,

I am using MSP to track earned value in my product development projects, and
it works pretty well (after some good help from this forum). However, when
doing so, I experience a conflict between reporting actual hours truthfully
and then present progress in the project to the steering group.

On the on hand, I want to be inputing actual worked hours, which I do using
the resource or task usage views. On the other hand I want to be able to
present the progress of the project to the steering group. Earned value is of
course one way of doing that, but most steering group members feel more
aquainted with a gantt-chart, preferably with progress bars or similar.

Personally I prefer doing a Life-cycle Breakdown Structure of my project
with design stages, rather than more traditional WBS. I am thinking that a
good idea would to specify some summary tasks, filter them and show them on a
one-page Gantt-chart together with the progress bars. Even better would of
course to include the baseline plan as well. What prevents me from doing this?

The problem is that even if for example production is at the end of the
project, we might do an early start on some activities that belongs to
production. Now, to report the real earned value, I need to input these
hours, but just a few weeks into the project, all actual Gantt bars tend to
start the first weeks of the project since a small part of that phase has
started. This makes the pretty useless, since all bars will be full length
(at least in terms of starting). The same goes for closing a phase, where
some action might have been delayed or treated as an exempt. The phase is 99%
complete, but the bar still goes on.

I realize that there are some different strategies on dealing with this, but
would greatly appreciate some advice and experience on the best ways to
combine true reporting of hours and presenting the project progress in a
Gantt-chart that gives you a good overview.

Thanks in advance,
Peter
 
J

Jim Aksel

The tracking Gantt allows display of progress along with a baseline.
Regarding the display of long tasks due to early starts, consider breaking
the tasks into several phases. You may specifically want to plan activities
up front such as "Manufacturing Planning" or the order of long lead items.

Putting all that under a life cycle heading of "Manufacturing" also does not
help, you may want to have another section for "Early Activities" ... just be
creative and give it a better name than I did.

Also, there are some companion products to MS Project that may give you a
different view that will be useful to your team. Kidasa Milestones
Professional 2008 is available from Kidasa.com. It's $250 and will combine
the traditional EV smoke stacks along with a baseline Gantt. They have a 30
day trial. They are a partner, check out the link below and look for
companion products.
--
If this post was helpful, please consider rating it.

Jim

Visit http://project.mvps.org/ for FAQs and more information
about Microsoft Project
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top