A
andrewandrew
1st question: Does anyone know if I can hack Project to get it to show a
progres line in relation to a Baseline 2, Baseline 3, or any baseline plan
other than the default?
2d question: Does anyone know if I can display a simple vertical line in the
Gantt Chart at a particular date for reference? (apart from maybe hacking the
nonworking time on the project calendar and using the nonworking time
shading.)
Thanks all!
progres line in relation to a Baseline 2, Baseline 3, or any baseline plan
other than the default?
2d question: Does anyone know if I can display a simple vertical line in the
Gantt Chart at a particular date for reference? (apart from maybe hacking the
nonworking time on the project calendar and using the nonworking time
shading.)
Thanks all!