K
ks2008
Dear All,
Review the question below.
I though the correct answer is "CV". In fact the correct answer is "SV"
May be I don't understand the question.
Could you you explain what we mean by, "monetary difference between the
current progress and the baseline plan of a particular task based on cost" ?
Thanks
KS
Question:
============
You are working on a project in MS Project. You want to view the exact
monetary difference between the current progress and the baseline plan of a
particular task based on cost.
Which earned value field should you use to view the required details ?
Review the question below.
I though the correct answer is "CV". In fact the correct answer is "SV"
May be I don't understand the question.
Could you you explain what we mean by, "monetary difference between the
current progress and the baseline plan of a particular task based on cost" ?
Thanks
KS
Question:
============
You are working on a project in MS Project. You want to view the exact
monetary difference between the current progress and the baseline plan of a
particular task based on cost.
Which earned value field should you use to view the required details ?