The plan is apparently calculating BCWS satisfactorily on "productive tasks",
( using Physical % Complete as the EV method for all tasks, and with the
progress input via Actual Work and Physical % Complete as independent
measures. The plan is baselined, status-dated and the baseline Start Date
has been exceeded ).
The immediate summary tasks to the "productive tasks" correctly sum the BCWS
values below.
Howewer, the higher level summary tasks - including the Project Summary Task
- fail to sum BCWS at all ( and show £0.00 ). All other EV fields sum
correctly in the Summary Tasks. F9 Calculate Now makes no improvement.
Project Professional 2002 (10.0.2002.0502)
Any ideas how I can get it to sum up ?
( using Physical % Complete as the EV method for all tasks, and with the
progress input via Actual Work and Physical % Complete as independent
measures. The plan is baselined, status-dated and the baseline Start Date
has been exceeded ).
The immediate summary tasks to the "productive tasks" correctly sum the BCWS
values below.
Howewer, the higher level summary tasks - including the Project Summary Task
- fail to sum BCWS at all ( and show £0.00 ). All other EV fields sum
correctly in the Summary Tasks. F9 Calculate Now makes no improvement.
Project Professional 2002 (10.0.2002.0502)
Any ideas how I can get it to sum up ?