C
cgoetz
Using Microsoft Project 2007, I am trying to look at the BCWS data for
resources on one project. When I select the Resource Usage View, it
properly displays the Work and Actual Cost data for each resource. Expanding
the resource shows all of the tasks and their corrrect Work and Actual Cost
data;however, the BCWS summary data for each resource is at best erratic!
Some resources show 0 BCWS in the Resource summary, but when the resource is
expanded the correct BCWS values are shown for each task. One Resource shows
a summary BCWS of over 7000 even though the Work is 1500 hours. Any ideas why
the BCWS summary is not functioning correctly in Resource Usage View?
Regards,
Charles Goetz
resources on one project. When I select the Resource Usage View, it
properly displays the Work and Actual Cost data for each resource. Expanding
the resource shows all of the tasks and their corrrect Work and Actual Cost
data;however, the BCWS summary data for each resource is at best erratic!
Some resources show 0 BCWS in the Resource summary, but when the resource is
expanded the correct BCWS values are shown for each task. One Resource shows
a summary BCWS of over 7000 even though the Work is 1500 hours. Any ideas why
the BCWS summary is not functioning correctly in Resource Usage View?
Regards,
Charles Goetz