Ganntt Bar

R

RPSnyder

Is there a way to show a single task as intermittent events on one Gannett bar line? Example a one day work session every two weeks. I have only been able to do this with the "split" function which is very laborious and difficult. Also you can do as multiple 0-day events with the split function. Example a task of regular deadlines, occurring every week that you want to show on the same line.
 
M

Mike Glen

Hi RPS,

Welcome to this Microsoft Project newsgroup :)

Try Insert/Recurring task.

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on:)

Mike Glen
MS Project MVP

RPSnyder said:
Is there a way to show a single task as intermittent events on one Gannett
bar line? Example a one day work session every two weeks. I have only been
able to do this with the "split" function which is very laborious and
difficult. Also you can do as multiple 0-day events with the split
function. Example a task of regular deadlines, occurring every week that you
want to show on the same line.
 

Ask a Question