Gantt and Resources problem

S

Schalk

I want my resource graph to display the same times as on my gantt chart,
currently if i schedule a resource to work 1,2,3,4,5,6,7,8 hours it shows
100% allocation, i want my resource graph to show me in % the duration that i
enter in my gantt chart duration column.
 
M

Mike Glen

Hi Schalk ,

Welcome to this Microsoft Project newsgroup :)

I think we need more information. What result are you trying to achieve?
The Duration column doesn't allow you to enter percentages, just times. The
Resource Graph shows the accumulation of assignments you've made. By
default, it shows the %Units allocated, but you can change this by
right-clicking in the graph area and selecting a different display like
Work.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials
 
J

Jan De Messemaeker

Hi,

To be precise, by default it shows peak units so if you have a 1 hr task @
100% it will show 100%.
Simply right-click on the graphical part and select %Allocation
HTH
 