Gantt chart view

R

Rob Stopa

When I look at the gantt chart view screen, it only presenst from Novemeber
onwards. I want it to start in August when the project starts but do not know
how.
Could someone please help?
 
R

Rob Stopa

Yes I have. The date if have set is correct, but is not the date which is
being represented in my View or when I print.
 
R

Rod Gill

To force a date range in a print:
Select File, Print
Set a date range then click Print
 
M

Mike Glen

Hi Rob,

Welcome to this Microsoft Project newsgroup :)

I suppose you've tried using the scroll bar at the bottom of the screen?
Does this not able you to view from August?

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 