aaghd said:
Is there any way to put more than one milestone on one row?

aaghd,
Only if it is a summary row. Subtask milestones can be rolled up to show
in their parent summary but for normal tasks (i.e. non-summary), only
one gantt bar (or milestone) can be displayed.

John
Project MVP
 
A

aaghd

Thank you for taking the time to respond. Your information was very helpful.

Have a wonderful weekend.
 