Barrie

Hi
I'm a bit of a novice so these questions may seem a bit juvenile.
I have set up a Project and created a resource calendar with non working
days etc. The Project still seems to assign tasks on some of those days
though.
Secondly - can I use Project to enter actual time and days spent ona task as
a kind of timesheet. EG I have one task of 4 days 23rd,24th,25th &26th April
- I actually did that task on 23rd,25th,26th &27th - can I chnge that easily?
Any advice gratefully received.
Thanks
BArrie
 
J

Jan De Messemaeker

Hi Barrie,

1. Did you assign the resoruce to the task?
2. Yes. Go to the Task Usage view,
Set Day as the minor timescale
Right-click on the right part
Click on Actual Work
In the left part inster the colulmn Remaining Work.

Now you're all set for a "Timesheet" application.

HTH

Jan De Messemaeker - MVP
 