I'm a bit of a novice so these questions may seem a bit juvenile.
I have set up a Project and created a resource calendar with non working
days etc. The Project still seems to assign tasks on some of those days
though.
Secondly - can I use Project to enter actual time and days spent ona task as
a kind of timesheet. EG I have one task of 4 days 23rd,24th,25th &26th April
- I actually did that task on 23rd,25th,26th &27th - can I chnge that easily?
Any advice gratefully received.