D
David McDermott
Same type of question orginally posted a week ago (23rd at
3.55am).
I am looking to incorporate graphical indicators into
Project and PWA. I have managed to do this but
unfortunately do not have them functioning correctly. I
have tried various kinds of formulas etc but none work as
required. What I want to do is to show when a task is
slipping. Ideally I want an indicator to show when the
remaining duration plus the current date is greater than
the finish date. Might settle for it showing if current
date is greater than finish date but don't see why you
shouldn't be able to do the first. Have tried playing
with formulas and functions but obviously have not managed
to get it right. If someone knows of how to do this
please explain the steps to me.
Also can status reports be sent to groups (i.e. project
manager group) instead of selecting individuals who need
to reply (otherwise some people may end up being sent
reports to fill in when they not managing projects so have
nothing to report).
Thanks in advance for any help.
Dave
3.55am).
I am looking to incorporate graphical indicators into
Project and PWA. I have managed to do this but
unfortunately do not have them functioning correctly. I
have tried various kinds of formulas etc but none work as
required. What I want to do is to show when a task is
slipping. Ideally I want an indicator to show when the
remaining duration plus the current date is greater than
the finish date. Might settle for it showing if current
date is greater than finish date but don't see why you
shouldn't be able to do the first. Have tried playing
with formulas and functions but obviously have not managed
to get it right. If someone knows of how to do this
please explain the steps to me.
Also can status reports be sent to groups (i.e. project
manager group) instead of selecting individuals who need
to reply (otherwise some people may end up being sent
reports to fill in when they not managing projects so have
nothing to report).
Thanks in advance for any help.
Dave