C
Chris
So I am trying to get a project (that has been maintained in excel)
implemented on project. I have a couple of questions about the workflow.
So our project has five or so contractors working to write a book. Each
contractor has about five tasks (write chapter, make edits, create chapter
questions, etc.) per chapter that they are assigned to write.
All of our contractors have given us the number of hours it is going to take
to perform each task and we have given them a due date for each task.
Incidently, each contractor has given us a flat rate price to complete all of
their tasks (not broken down by task). These contractors have other jobs, so
the are not committing 100% of their time on the project. They might even be
working weekends. That is it. so in the spreadsheet, we have the number of
hours for task, the assignment, the due date, and if the task has been
started or completed.
So I have the project all set up in MS Project. I have all the tasks filled
out and the Resources added to the resource sheet. My issues are now:
What do I put in for the duration, units, and work? We really don't know
when they are going to start the task, we just know what the due date we
assigned is, and how much work it is going to take. We know that the
contractors have other jobs, so are not full-time and might be working during
non-standard hours (nights/weekends).
Is there a way to set this up so that we can record percentages of
completion. That way we might be able to notice red flags (e.g., the task
requires 16 hours of work and there is only one day left for due date).
Going forward (I am not pm on this project, just helping to get it under
control), what is the best way to handle contractors like this if we intend
to track the project in MS Project? I was thinking we should get them to
commit to some kind of work and duration and let us schedule a start and
finish date for them?
Project is a great tool and I am still a newbie, but have been reading a lot
of great books on the topic. I am hoping one of you brilliant project
experts can help me get this project going correctly in MS Project.
Thanks for taking the time to read and hopefully respond.
Chris
implemented on project. I have a couple of questions about the workflow.
So our project has five or so contractors working to write a book. Each
contractor has about five tasks (write chapter, make edits, create chapter
questions, etc.) per chapter that they are assigned to write.
All of our contractors have given us the number of hours it is going to take
to perform each task and we have given them a due date for each task.
Incidently, each contractor has given us a flat rate price to complete all of
their tasks (not broken down by task). These contractors have other jobs, so
the are not committing 100% of their time on the project. They might even be
working weekends. That is it. so in the spreadsheet, we have the number of
hours for task, the assignment, the due date, and if the task has been
started or completed.
So I have the project all set up in MS Project. I have all the tasks filled
out and the Resources added to the resource sheet. My issues are now:
What do I put in for the duration, units, and work? We really don't know
when they are going to start the task, we just know what the due date we
assigned is, and how much work it is going to take. We know that the
contractors have other jobs, so are not full-time and might be working during
non-standard hours (nights/weekends).
Is there a way to set this up so that we can record percentages of
completion. That way we might be able to notice red flags (e.g., the task
requires 16 hours of work and there is only one day left for due date).
Going forward (I am not pm on this project, just helping to get it under
control), what is the best way to handle contractors like this if we intend
to track the project in MS Project? I was thinking we should get them to
commit to some kind of work and duration and let us schedule a start and
finish date for them?
Project is a great tool and I am still a newbie, but have been reading a lot
of great books on the topic. I am hoping one of you brilliant project
experts can help me get this project going correctly in MS Project.
Thanks for taking the time to read and hopefully respond.
Chris