Having resources on a team

C

Chris

I have a master resource pool, and I am trying to create a "team" of resources where all I have to do is type in the # of the team for resource assignment and it will bring up the team of resources that I want for that task. How do I go about building this team of resources, so no matter what task I assign the team too; it will show the team tasks under each individual resource's assignement

Thank
Chris
 
J

Jan De Messemaeker

Hi,

This is not standard, you will have to code it in VBA.
HTH
--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
Project Management Consultancy
Prom+ade BVBA
32-495-300 620
Chris said:
I have a master resource pool, and I am trying to create a "team" of
resources where all I have to do is type in the # of the team for resource
assignment and it will bring up the team of resources that I want for that
task. How do I go about building this team of resources, so no matter what
task I assign the team too; it will show the team tasks under each
individual resource's assignement?
 