Rick Williams
I am attempting to use Risk+ with Project 2003 (desktop version, not
server). Risk+ uses the Duration1 field to hold the Optimistic duration and
Duration2 to hold the Pessimistic estimate. In my schedule, though (58,000+
tasks), Duration1 is not editable - in fact, the values are greyed out when
I select the cell. Duration2, 3, etc. can all be edited, but not Duration1.
Can anyone please help me with this? How can I 'fix' Duration1? I have used
MS Project since it was introduced, but I have never seen this problem.
There are no formulas in Duration1, BTW.
Thanks,
Rick Williams
NASA - Marshall Space Flight Center
server). Risk+ uses the Duration1 field to hold the Optimistic duration and
Duration2 to hold the Pessimistic estimate. In my schedule, though (58,000+
tasks), Duration1 is not editable - in fact, the values are greyed out when
I select the cell. Duration2, 3, etc. can all be edited, but not Duration1.
Can anyone please help me with this? How can I 'fix' Duration1? I have used
MS Project since it was introduced, but I have never seen this problem.
There are no formulas in Duration1, BTW.
Thanks,
Rick Williams
NASA - Marshall Space Flight Center